Slack time is equal to:
A) the difference between an activity's latest and earliest expected completion time
B) the latest expected completion time
C) the difference between the start time and realistic time for each activity
D) the sum of an activity's latest and earliest expected completion time
Correct Answer:
Verified
Q103: In OOSAD,one outcome of defining the overall
Q104: Realistic time is:
A)the maximum period of time
Q105: What would be the estimated time for
Q106: In OOSAD,each project iteration has all of
Q107: When a project manager divides a system
Q109: Which of the following is a true
Q110: In OOSAD,iterations are normally:
A)five weeks
B)ten weeks
C)eleven weeks
D)two
Q111: What would be the estimated time for
Q112: A critical path is:
A)a sequence of activities
Q113: Optimistic time is:
A)the maximum period of time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents