Which of the following is a true statement regarding network diagrams?
A) The critical path of a network diagram is represented by the sequence of connected activities that produce the longest overall time period.
B) All activities with a slack time equal to zero are on the critical path.
C) Nodes not on the critical path can be delayed (for some amount of time) without delaying the final completion of the project.
D) All of the above.
Correct Answer:
Verified
Q104: Realistic time is:
A)the maximum period of time
Q105: What would be the estimated time for
Q106: In OOSAD,each project iteration has all of
Q107: When a project manager divides a system
Q108: Slack time is equal to:
A)the difference between
Q110: In OOSAD,iterations are normally:
A)five weeks
B)ten weeks
C)eleven weeks
D)two
Q111: What would be the estimated time for
Q112: A critical path is:
A)a sequence of activities
Q113: Optimistic time is:
A)the maximum period of time
Q114: Pessimistic time is:
A)the maximum period of time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents