What would be the estimated time for completion if time estimates for installation are as follows: optimistic = 1 week;pessimistic = 1 week;realistic = 1 week?
A) 5 weeks
B) 6 weeks
C) 3 weeks
D) 1 week
Correct Answer:
Verified
Q100: Any person,group of people,piece of equipment,or material
Q101: The amount of time that an activity
Q102: What would be the estimated time for
Q103: In OOSAD,one outcome of defining the overall
Q104: Realistic time is:
A)the maximum period of time
Q106: In OOSAD,each project iteration has all of
Q107: When a project manager divides a system
Q108: Slack time is equal to:
A)the difference between
Q109: Which of the following is a true
Q110: In OOSAD,iterations are normally:
A)five weeks
B)ten weeks
C)eleven weeks
D)two
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents