What would be the estimated time for completion if time estimates for programming are as follows: optimistic = 4 weeks;pessimistic = 6 weeks;realistic = 5 weeks?
A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
Correct Answer:
Verified
Q97: When comparing a Gantt chart to a
Q98: A diagram that depicts project activities and
Q99: Which of the following states correctly the
Q100: Any person,group of people,piece of equipment,or material
Q101: The amount of time that an activity
Q103: In OOSAD,one outcome of defining the overall
Q104: Realistic time is:
A)the maximum period of time
Q105: What would be the estimated time for
Q106: In OOSAD,each project iteration has all of
Q107: When a project manager divides a system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents