A critical path is:
A) a sequence of activities whose order and durations indirectly affect the completion date of a project
B) a sequence of activities whose order and durations directly affect the completion date of a project
C) a sequence of activities whose order must be performed in parallel
D) a sequence of activities whose duration cannot last more than 40 percent of the time allotted to the project
Correct Answer:
Verified
Q107: When a project manager divides a system
Q108: Slack time is equal to:
A)the difference between
Q109: Which of the following is a true
Q110: In OOSAD,iterations are normally:
A)five weeks
B)ten weeks
C)eleven weeks
D)two
Q111: What would be the estimated time for
Q113: Optimistic time is:
A)the maximum period of time
Q114: Pessimistic time is:
A)the maximum period of time
Q115: Which of the following is true regarding
Q116: Automated tools available to help you manage
Q117: A _ is a systems analyst with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents