An activity,A,has two succeeding activities,B and C.Given the following information,determine the latest starting time for activity A. EF B = 15,EF C = 17,LF B = 24,LF C = 27; activity times are A = 4,B = 6,C = 8.
A) 14
B) 15
C) 16
D) 17
E) 18