Which of the following is used to compute the earliest finish times once the earliest start times are calculated for an activity on a precedence network?
A) Expected activity duration
B) Activity slack time
C) Activities that are on the critical path
D) Variance in project duration
E) Maximum project duration
Correct Answer:
Verified
Q63: The project management technique that is repeated
Q64: A relatively simple tool for planning and
Q65: There are four activities on the critical
Q66: A PERT/CPM activity has an optimistic duration
Q67: Concerning PERT and CPM,which of the following
Q69: In a precedence network the critical path
Q70: In precedence network analysis,knowing the slack time
Q71: In the probabilistic approach to precedence network
Q72: Which of the following is not an
Q73: Given this information about activity B: ES
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents