Concerning PERT and CPM,which of the following statements is correct?
A) These are two different names for what is essentially the same technique.
B) CPM tends to focus more on the critical path.
C) PERT gives a clearer indication of activity slack,while CPM gives a better picture of path slack.
D) Because of its recent discovery,much less is known about CPM than PERT.
E) Neither provides as much detail as a Gantt chart.
Correct Answer:
Verified
Q62: The principal advantage a Gantt chart has
Q63: The project management technique that is repeated
Q64: A relatively simple tool for planning and
Q65: There are four activities on the critical
Q66: A PERT/CPM activity has an optimistic duration
Q68: Which of the following is used to
Q69: In a precedence network the critical path
Q70: In precedence network analysis,knowing the slack time
Q71: In the probabilistic approach to precedence network
Q72: Which of the following is not an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents