In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:
A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.
Correct Answer:
Verified
Q56: Risk assessment is part of the project
Q57: Project planning determines how the project is
Q58: Which of the following is not involved
Q59: Quality tools such as control charts can
Q60: The main determinant of the way PERT/CPM
Q62: The principal advantage a Gantt chart has
Q63: The project management technique that is repeated
Q64: A relatively simple tool for planning and
Q65: There are four activities on the critical
Q66: A PERT/CPM activity has an optimistic duration
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents