Solved

In the Probabilistic Approach to Precedence Network Analysis,the Duration Estimate

Question 61

Multiple Choice

In the probabilistic approach to precedence network analysis,the duration estimate that is given the highest weighting in calculating the expected duration for an activity is:


A) duration of the immediately prior activity.
B) duration of the immediately following activity.
C) most likely duration.
D) optimistic duration.
E) pessimistic duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents