The main determinant of the way PERT/CPM networks are used is whether activity/work package durations are ________ or ____________.
A) statistical,actual
B) probabilistic or deterministic.
C) normal,variable
D) actual,variable
E) probabilistic or statistical
Correct Answer:
Verified