Which of the following is not a form of risk reduction in project management?
A) Backup systems
B) Outsourcing components of the project
C) Frequent monitoring of project activities
D) Expand the project scope to reduce external dependencies
E) Improving communications
Correct Answer:
Verified
Q50: Which of the following is not part
Q51: A hierarchical listing of what must be
Q52: Scope creep refers to the tendency for
Q53: Which of the following is the last
Q54: The optimum project length in crashing occurs
Q56: Risk assessment is part of the project
Q57: Project planning determines how the project is
Q58: Which of the following is not involved
Q59: Quality tools such as control charts can
Q60: The main determinant of the way PERT/CPM