When developing probabilistic estimates of project duration,it is necessary to know which of the following?
A) The mean and variance of every activity
B) The mean and variance of activities on the critical path
C) The standard deviation of activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity durations
Correct Answer:
Verified
Q74: Activity 4 in a network diagram has
Q75: Activity 7 is directly preceded by two
Q76: Besides project activities,the primary information that all
Q77: Which of the following is not an
Q78: Which of the following is not a
Q79: Activity C has an early start time
Q81: Which of the following is not an
Q82: The owner of Ace Building Co.is about
Q83: The Project Manager is about to begin
Q84: A project manager for Durable Construction Co.is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents