Activity 7 is directly preceded by two activities-activity 5 and activity 6.Activity 5 has an expected duration of five and an ES time of six.Activity 6 has an expected duration of seven and an ES time of seven.Activity 7 has an expected duration of 10.The ES for activity 7 is:
A) 11
B) 14
C) 21
D) 24
E) 25
Correct Answer:
Verified
Q70: In precedence network analysis,knowing the slack time
Q71: In the probabilistic approach to precedence network
Q72: Which of the following is not an
Q73: Given this information about activity B: ES
Q74: Activity 4 in a network diagram has
Q76: Besides project activities,the primary information that all
Q77: Which of the following is not an
Q78: Which of the following is not a
Q79: When developing probabilistic estimates of project duration,it
Q79: Activity C has an early start time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents