Given the portion of the network shown above,based on the activity durations shown what is the earliest finish time for activity D,if the earliest start time of B is 12,and the earliest start time of C is 13?
A) 19
B) 20
C) 21
D) 22
E) 23
Correct Answer:
Verified
Q65: There are four activities on the critical
Q68: Which of the following is used to
Q74: An activity,A,has two succeeding activities,B and C.Given
Q76: Q80: In "crashing",a project manager will generally focus Q81: Which of the following is not an Q81: What is the estimated expected (mean)duration for Q83: What is the estimated expected (mean)duration for Q86: What is the probability that this project Q95: Uncontrolled growth in the number of activities