A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology?
A) 9.0
B) 7.5
C) 4.5
D) 6.0
Correct Answer:
Verified
Q60: Which statement about critical chain project management
Q61: A project is represented by the
Q62: A project consists of four consecutive
Q63: A project consists of four consecutive
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q66: A project consists of four consecutive
Q67: A project is represented by the
Q68: A project consists of six consecutive
Q69: A project is represented by the
Q70: A project consists of four consecutive