Which statement about critical chain project management is BEST?
A) CCPM is a complete solution to current project management scheduling needs.
B) In a multiproject environment where resources are shared,it is impossible to avoid multitasking.
C) There is substantial large-scale empirical research that confirms the efficacy of CCPM.
D) Lack of milestones within CCPM make coordination with external suppliers and subcontractors much easier.
Correct Answer:
Verified
Q55: Which statement about critical chain methodology is
Q56: Once the organization elevates its constraint,its system
Q57: Your next project consists of 8 consecutive
Q58: The critical chain is usually the same
Q59: A project consists of four activities
Q61: A project is represented by the
Q62: A project consists of four consecutive
Q63: A project consists of four consecutive
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q65: A project is represented by the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents