A Project Consists of Four Consecutive Tasks That Have Average

Question 62

Multiple Choice

A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Newbold's model to determine the aggregated buffer of one standard deviation for this project.  Activity  Average  Worst-Case X1220Y2025Z1424W1826\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \mathrm { X } & 12 & 20 \\\hline \mathrm { Y} & 20 & 25 \\\hline \mathrm { Z} & 14 & 24 \\\hline \mathrm { W } & 18 & 26 \\\hline\end{array}


A) 31 days
B) 16 days
C) 8 days
D) 5 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents