A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology?
A) 9.0
B) 2.25
C) 4.5
D) 6.75
Correct Answer:
Verified
Q56: Once the organization elevates its constraint,its system
Q57: Your next project consists of 8 consecutive
Q58: The critical chain is usually the same
Q59: A project consists of four activities
Q60: Which statement about critical chain project management
Q62: A project consists of four consecutive
Q63: A project consists of four consecutive
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q65: A project is represented by the
Q66: A project consists of four consecutive
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents