A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?
A) 3.5 days
B) 2.5 days
C) 1.5 days
D) 0.5 days
Correct Answer:
Verified
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q65: A project is represented by the
Q66: A project consists of four consecutive
Q67: A project is represented by the
Q68: A project consists of six consecutive
Q70: A project consists of four consecutive
Q71: A project is represented by the
Q72: A project is represented by the
Q73: A project is represented by the
Q74: A project is represented by the