A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?
A) 4 days
B) 3 days
C) 2 days
D) 1 days
Correct Answer:
Verified
Q67: A project is represented by the
Q68: A project consists of six consecutive
Q69: A project is represented by the
Q70: A project consists of four consecutive
Q71: A project is represented by the
Q73: A project is represented by the
Q74: A project is represented by the
Q75: A project consists of six consecutive
Q76: A project is represented by the
Q77: The buffers supplied to non-critical paths in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents