A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach.
A) 8.5 days
B) 17 days
C) 24.5 days
D) 34 days
Correct Answer:
Verified
Q66: A project consists of four consecutive
Q67: A project is represented by the
Q68: A project consists of six consecutive
Q69: A project is represented by the
Q70: A project consists of four consecutive
Q72: A project is represented by the
Q73: A project is represented by the
Q74: A project is represented by the
Q75: A project consists of six consecutive
Q76: A project is represented by the