There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to
A) 2.
B) 4.
C) 8.
D) 16.
E) 64.
Correct Answer:
Verified
Q63: Activity 4-5 in a network diagram has
Q64: When developing probabilistic estimates of project duration,
Q65: The basis for use of the beta
Q66: Which of the following are limitations of
Q67: A PERT/CPM activity has an optimistic time
Q69: Gantt charts are most closely associated with
A)JIT.
B)PERT.
C)MRP.
D)MRPII.
E)Six
Q70: In project network analysis, "slack" refers to
Q71: A node has one entering activity, a,
Q72: There are four activities on the critical
Q73: In the probabilistic approach to project network