A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is
A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.
Correct Answer:
Verified
Q62: The project management strategy of injecting additional
Q63: Activity 4-5 in a network diagram has
Q64: When developing probabilistic estimates of project duration,
Q65: The basis for use of the beta
Q66: Which of the following are limitations of
Q68: There are four activities on the critical
Q69: Gantt charts are most closely associated with
A)JIT.
B)PERT.
C)MRP.
D)MRPII.
E)Six
Q70: In project network analysis, "slack" refers to
Q71: A node has one entering activity, a,
Q72: There are four activities on the critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents