When developing probabilistic estimates of project duration, it is necessary to know which of the following?
A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times
Correct Answer:
Verified
Q59: In a project network, the critical path
Q60: A popular visual tool for planning and
Q61: Which of the following is not a
Q62: The project management strategy of injecting additional
Q63: Activity 4-5 in a network diagram has
Q65: The basis for use of the beta
Q66: Which of the following are limitations of
Q67: A PERT/CPM activity has an optimistic time
Q68: There are four activities on the critical
Q69: Gantt charts are most closely associated with
A)JIT.
B)PERT.
C)MRP.
D)MRPII.
E)Six
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents