Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately
A) 5.
B) 6.
C) 7.
D) 8.
E) 9.
Correct Answer:
Verified