In project network analysis, "slack" refers to the difference between
A) observed and predicted times.
B) optimistic and pessimistic times.
C) mean and modal times.
D) finish and start times.
E) latest and earliest times.
Correct Answer:
Verified
Q65: The basis for use of the beta
Q66: Which of the following are limitations of
Q67: A PERT/CPM activity has an optimistic time
Q68: There are four activities on the critical
Q69: Gantt charts are most closely associated with
A)JIT.
B)PERT.
C)MRP.
D)MRPII.
E)Six
Q71: A node has one entering activity, a,
Q72: There are four activities on the critical
Q73: In the probabilistic approach to project network
Q74: Which of the following are advantages of
Q75: A project is represented by the following