Solved

You Have Collected the Data for a Time-Cost CPM Scheduling

Question 70

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect)  project cost? A) $2,150 B) $2,300 C) $2,400 D) $2,450 E) $2,500 The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be
$100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost?


A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents