Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost?
A) Total time is 13 days, total cost is $1200
B) Total time is 12 days, total cost is $1700
C) Total time is 11 days, total cost is $1600
D) Total time is 10 days, total cost is $1750
E) Total time is 9 days, total cost is $1700
Correct Answer:
Verified
Q41: Which of the following is a graphic
Q57: A series of projects that are organized
Q58: You are looking at a chart that
Q60: A simple project listing of five activities,
Q61: You have collected the data for a
Q63: You have the following time and cost
Q64: You know when you have arrived at
Q65: Below are the data for a Time-Cost
Q66: Below are the data for a Time-Cost
Q67: You have just performed a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents