You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?
A) You have found the critical path
B) You have run out of crash time
C) You no longer have a linear relationship with costs
D) You have reached the minimum total cost
E) You have run out of crash costs
Correct Answer:
Verified