Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost?
A) Total time is 10 days, total cost is $2500
B) Total time is 9 days, total cost is $2300
C) Total time is 8 days, total cost is $2750
D) Total time is 8 days, total cost is $1850
E) Total time is 9 days, total cost is $2350
Correct Answer:
Verified
Q60: A simple project listing of five activities,
Q61: You have collected the data for a
Q62: Below are the data for a Time-Cost
Q63: You have the following time and cost
Q63: In CPM analysis, it is generally expected
Q64: You know when you have arrived at
Q65: Below are the data for a Time-Cost
Q67: You have just performed a CPM analysis
Q69: A listing of immediate predecessor activities is
Q70: You have collected the data for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents