You are looking at a chart that has the terms BCWS, BCWP and AC indicating lines on the chart.What kind of chart are you looking at?
A) Gantt Chart
B) PERT Chart
C) Bar/Milestone Chart
D) Total Program Cost Breakdown
E) EVM Chart
Correct Answer:
Verified