For an activity in a CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is ?
A) The activity's late start must happen before its early start
B) The activity is on the critical path
C) The slack for this activity is 20
D) The duration of this task is zero
E) The duration of this task is 20
Correct Answer:
Verified
Q41: Which of the following is a graphic
Q45: An advantage of a pure project where
Q50: What is a work breakdown structure?
A)A list
Q52: A company must perform a maintenance project
Q53: For an activity in a CPM analysis,
Q54: A simple project listing of five activities
Q56: PERT is an abbreviation for which of
Q57: A series of projects that are organized
Q58: You are looking at a chart that
Q60: A simple project listing of five activities,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents