An easy way to assess team member interest in various aspects of a project before assigning responsibility is:
A) Create a responsibility matrix and fill in people's names.
B) Have each team member use a separate color during mind mapping and then look at the pen colors on the WBS mind map and see where team members' dominant interests seem to be.
C) Conduct an email survey.
D) Use a project-involvement matrix.
E) Create an OBS.
Correct Answer:
Verified
Q2: A project team is using the PERT
Q3: Which of the following is a reasonable
Q4: All of the following are advantages to
Q5: Which of the following depends) on the
Q6: Which of the following WBS formats is
Q7: A consumer electronics company is planning a
Q8: Which of the following is not a
Q9: A new project manager is taking over
Q10: Which of these is the best guideline
Q11: A national circus organization performs in outdoor
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents