A project team is using the PERT method to estimate time durations for tasks. One of the tasks has the following parameters:
to = 25 days
tp = 50 days
tm = 30 days
Based on these parameters, expected time for this task would be:
A) 32.5 days
B) 42.5 days
C) 4.17 days
D) 37.5 days
E) 30 days
Correct Answer:
Verified