All of the Following Are Advantages to Including the Team

Question 4

Multiple Choice

All of the following are advantages to including the team in creating the WBS, EXCEPT:


A) They are the content experts and best equipped to know what is involved in generating each deliverable
B) Team members will gain a total view of the project through their involvement in creating the WBS.
C) Participation in the creation of the WBS builds team members' commitment to the project.
D) Participation in the creation of the WBS can bring conflicting views to the surface before it is too late to address them
E) All of the above are advantages.

Correct Answer: