A Consumer Electronics Company Is Planning a 16-City Product Show

Question 7

Multiple Choice

A consumer electronics company is planning a 16-city product show in Central and South America. The 25 crewmembers have committed to working the entire tour. Set-up time in the first city, Managua, is estimated to require 200 hours of calendar time, and based on historical data, the project manager is forecasting a learning rate of 85%. Based on learning curve concepts, what is the estimate for the time needed to set up in the 16th city, Caracas? Figures rounded to 2 places to the right of decimal.)


A) 170 hours
B) 122.83 hours
C) 104.40 hours
D) 88.74 hours
E) 7.75 hours
F) None of these. The answer is ______________hours show your work) .

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents