A consumer electronics company is planning a 16-city product show in Central and South America. The 25 crewmembers have committed to working the entire tour. Set-up time in the first city, Managua, is estimated to require 200 hours of calendar time, and based on historical data, the project manager is forecasting a learning rate of 85%. Based on learning curve concepts, what is the estimate for the time needed to set up in the 16th city, Caracas? Figures rounded to 2 places to the right of decimal.)
A) 170 hours
B) 122.83 hours
C) 104.40 hours
D) 88.74 hours
E) 7.75 hours
F) None of these. The answer is ______________hours show your work) .
Correct Answer:
Verified
Q2: A project team is using the PERT
Q3: Which of the following is a reasonable
Q4: All of the following are advantages to
Q5: Which of the following depends) on the
Q6: Which of the following WBS formats is
Q8: Which of the following is not a
Q9: A new project manager is taking over
Q10: Which of these is the best guideline
Q11: A national circus organization performs in outdoor
Q12: Which WBS approach is most likely to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents