Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
A) One; $400
B) One; $6,800
C) Two; $1,000
D) Two; $5,000
E) One or two should be crashed; $1,400
Correct Answer:
Verified
Q59: Which of the following statements regarding CPM
Q60: A simple CPM network has three activities,
Q61: A project being analyzed by PERT has
Q64: A contractor's project being analyzed by PERT
Q66: A project whose critical path has an
Q68: A PERT project has 45 activities, 19
Q68: Two critical path activities are candidates
Q69: A project being analyzed by PERT has
Q78: If an activity whose normal duration is
Q87: Analysis of a PERT problem shows the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents