A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is
A) -2.00
B) 0.0227
C) 0.1058
D) 0.4773
E) 0.9773
Correct Answer:
Verified
Q63: A project whose critical path has an
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q66: A project whose critical path has an
Q67: An activity on a PERT network has
Q69: If an activity whose normal duration is
Q70: Two critical path activities are candidates
Q71: Two critical path activities are candidates
Q87: Analysis of a PERT problem shows the
Q97: Contract requirements state that a project must
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents