Solved

Two Critical Path Activities Are Candidates for Crashing on a CPM

Question 68

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.  Activity  Normal Time  Normal Cost  Crash Time  Crash Cost  B 4 days $6,0003 days $8,000 C 6 days $4,0004 days $6,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \text { Crash Time } & \text { Crash Cost } \\\hline \text { B } & 4 \text { days } & \$ 6,000 & 3 \text { days } & \$ 8,000 \\\hline \text { C } & 6 \text { days } & \$ 4,000 & 4 \text { days } & \$ 6,000 \\\hline\end{array}


A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents