Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000
Correct Answer:
Verified
Q62: Which of the following statements regarding time-cost
Q64: A contractor's project being analyzed by PERT
Q64: Two critical path activities are candidates
Q66: A project whose critical path has an
Q68: A PERT project has 45 activities, 19
Q69: A project being analyzed by PERT has
Q71: If an activity whose normal duration is
Q73: An activity on a PERT network has
Q78: If an activity whose normal duration is
Q125: A network has been crashed to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents