A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D = 5, E = 4, F = 9.
A) The critical path is D-E-F, duration 18.
B) The critical path is D-F, duration 14.
C) Slack at D is 4 units.
D) Slack at E is 4 units.
E) The network has two critical paths.
Correct Answer:
Verified
Q47: Activity R on a CPM network has
Q53: Activity D on a CPM network has
Q57: The Beta distribution is used in project
Q59: Which of the following statements regarding CPM
Q61: A project being analyzed by PERT has
Q64: Two critical path activities are candidates
Q66: A project whose critical path has an
Q78: If an activity whose normal duration is
Q87: Analysis of a PERT problem shows the
Q96: The time an activity will take assuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents