The Beta distribution is used in project management to
A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) calculate slack for activities on the shortest path.
Correct Answer:
Verified
Q47: Activity R on a CPM network has
Q53: Activity D on a CPM network has
Q53: Which of the following statements regarding PERT
Q59: Which of the following statements regarding CPM
Q60: A simple CPM network has three activities,
Q61: A project being analyzed by PERT has
Q87: Analysis of a PERT problem shows the
Q89: The _ distribution is used by PERT
Q96: The time an activity will take assuming
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents