Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of given times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer:
Verified
Q42: The critical path for the network
Q43: The Beta distribution is used in project
Q44: A simple CPM network has three activities,
Q45: Which of the following statements regarding CPM
Q46: Which of the following statements regarding PERT
Q49: A project being analyzed by PERT has
Q51: A simple CPM network has five activities,
Q52: The Beta distribution is used in project
Q53: Activity D on a CPM network has
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents