A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths through this network.
E) None of these statements is true.
Correct Answer:
Verified
Q46: Which of the following statements regarding PERT
Q47: Activity R on a CPM network has
Q49: A project being analyzed by PERT has
Q52: The Beta distribution is used in project
Q53: Activity D on a CPM network has
Q53: The critical path for the network
Q56: The critical path for the network
Q89: The _ distribution is used by PERT
Q96: The time an activity will take assuming
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!