A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.
A) The critical path is D-E-F, duration 15.
B) The critical path is D-F, duration 12.
C) Slack at D is 3 units.
D) Slack at E is 3 units.
E) Both A and C are true.
Correct Answer:
Verified
Q42: The critical path for the network
Q43: The Beta distribution is used in project
Q45: Which of the following statements regarding CPM
Q46: Which of the following statements regarding PERT
Q47: Activity R on a CPM network has
Q49: A project being analyzed by PERT has
Q51: Which of the following statements regarding critical
Q82: The expected activity time in PERT analysis
Q100: Which of the following statements regarding PERT
Q109: A project manager is interested in crashing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents