Which of the following statements regarding CPM networks is true?
A) There can be multiple critical paths on the same project, all with different durations.
B) The early finish of an activity is the latest early start of all preceding activities.
C) The late start of an activity is its late finish plus its duration.
D) If a specific project has multiple critical paths, all of them will have the same duration.
E) If a specific project has multiple critical paths, all of them will have negative slack.
Correct Answer:
Verified
Q47: Activity R on a CPM network has
Q53: Activity D on a CPM network has
Q57: The Beta distribution is used in project
Q60: A simple CPM network has three activities,
Q61: A project being analyzed by PERT has
Q64: Two critical path activities are candidates
Q66: A project whose critical path has an
Q87: Analysis of a PERT problem shows the
Q89: The _ distribution is used by PERT
Q96: The time an activity will take assuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents