Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) "Project Crashing" shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) All of the above are false.
Correct Answer:
Verified
Q46: Which of the following statements regarding PERT
Q47: Activity R on a CPM network has
Q52: The Beta distribution is used in project
Q60: Which of the following statements regarding PERT
Q66: Two critical path activities are candidates for
Q67: An activity on a PERT network has
Q78: If an activity whose normal duration is
Q79: An activity on a PERT network has
Q80: Which of these statements regarding time-cost tradeoffs
Q97: Contract requirements state that a project must
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents