Which of the following statements regarding PERT analysis is true?
A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) None of the above is true.
Correct Answer:
Verified
Q48: A simple CPM network has three activities,A,B,and
Q56: The critical path for the network
Q57: Which of the following statements concerning CPM
Q61: A local project being analyzed by PERT
Q62: An activity on a PERT network has
Q63: A project whose critical path has an
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q89: The _ distribution is used by PERT
Q90: In a PERT network, non-critical activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents