Which of the following statements concerning CPM activities is False?
A) The early finish of an activity is the early start of that activity plus its duration.
B) The late finish is the earliest of the late start times of all successor activities.
C) The late start of an activity is its late finish less its duration.
D) The late finish of an activity is the earliest late start of all preceding activities.
E) The early start of an activity is the latest early finish of all preceding activities.
Correct Answer:
Verified
Q48: A simple CPM network has three activities,A,B,and
Q52: The Beta distribution is used in project
Q53: The critical path for the network
Q56: The critical path for the network
Q60: Which of the following statements regarding PERT
Q61: A local project being analyzed by PERT
Q62: An activity on a PERT network has
Q89: The _ distribution is used by PERT
Q90: In a PERT network, non-critical activities that
Q96: The time an activity will take assuming
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents