An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is
A) 2.00
B) 2.33
C) 2.67
D) 8.00
E) none of these
Correct Answer:
Verified
Q48: A simple CPM network has three activities,A,B,and
Q57: Which of the following statements concerning CPM
Q60: Which of the following statements regarding PERT
Q61: A local project being analyzed by PERT
Q63: A project whose critical path has an
Q64: A contractor's project being analyzed by PERT
Q65: _ is an organization formed to ensure
Q66: A project whose critical path has an
Q67: An activity on a PERT network has
Q90: In a PERT network, non-critical activities that