Which of these statements regarding time-cost tradeoffs in CPM networks is true?
A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration, but noncritical, activities.
C) Activities not on the critical path can never be on the critical path, even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) None of the above is true.
Correct Answer:
Verified
Q9: What are the three phases of a
Q27: Describe some of the challenges faced in
Q35: What is a project organization?
Q50: The _ is the computed longest time
Q71: _ is the amount of time an
Q76: A project being analyzed by PERT has
Q78: If an activity whose normal duration is
Q79: An activity on a PERT network has
Q113: What was the name of the construction
Q125: A network has been crashed to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents